Stoner Trail Storage
100 MW storage in Fulton, NY · In queue since October 2024 · Proposed COD August 2028
100 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-01
The Stoner Trail Storage project is a proposed 100 MW battery storage project located in Fulton County, New York. Developed by Granada Solar, LLC, the project is interconnected within the New York Independent System Operator (NYISO) queue as entry NYISO-C24-332, with a queue entry date of October 9, 2024. The proposed commercial operation date is August 1, 2028.
The project consists of 100 MW of battery storage capacity. Interconnection will be made at the Inghams-Stoner 115kV line 9 and Meco-Maple Ave 115kV line 22. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NY
County
Fulton
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Granada Solar, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Inghams-Stoner 115kV line 9 and Meco-Maple Ave 115kV line 22
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Stoner Trail Storage