Aria Storage 1
100 MW storage in Dutchess, NY · In queue since October 2024 · Proposed COD December 2028
100 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
Aria Storage 1 is a proposed 100 MW battery storage project located in Dutchess County, New York. Developed by Terra-Gen Development, LLC, the project is interconnected to the ConEd utility via the East Fishkill 345 kV substation. It is currently listed as active in the New York Independent System Operator (NYISO) interconnection queue under queue ID NYISO-C24-337, with an entry date of October 10, 2024.
The proposed commercial operation date for Aria Storage 1 is December 1, 2028.
Generated from interconnection queue and public data sources
State
NY
County
Dutchess
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Terra-Gen Development, LLC
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
East Fishkill 345 kV substation
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE G
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- E_FISHKILL___LBMP
- POI Substation
- East Fishkill Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.