Richland III Solar
79.9 MW generation in Oswego, NY · In queue since October 2024 · Proposed COD February 2029
79.9 MW
Capacity
1
Components
Solar
1y 7m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-02-01
The Richland III Solar project is a proposed 79.9 MW solar generation project located in Oswego County, New York. Developed by RIC Development, LLC, the project is in the New York ISO (NYISO) interconnection queue as entry NYISO-C24-349-005, with a queue entry date of October 14, 2024. The proposed commercial operation date is February 1, 2029. The project is linked to the existing Richland III Solar operating plant (EIA ID 68663).
The Richland III Solar project has been the subject of recent news coverage, with 20 articles appearing in the press. These articles primarily focus on industry-related topics, with additional coverage of grid and regulatory aspects.
Generated from interconnection queue and public data sources
State
NY
County
Oswego
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
RIC Development, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Indeck Oswego - Tar Hill Line 2 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- NYISO Zone D
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- EAST_PULASKI___ESR