Bayonne Energy Storage II
400 MW storage in Hudson, NJ · In queue since October 2024 · Proposed COD December 2029
400 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
The Bayonne Energy Storage II project is a proposed 400 MW battery storage facility located in Hudson County, New Jersey. The project, developed by AMBAR POWER HOLDCO LLC, is interconnected to the ConED utility and participates in the NYISO interconnection queue under queue ID NYISO-C24-355. The project entered the queue on October 15, 2024, with a proposed commercial operation date of December 1, 2029.
The project is currently listed as active in the NYISO queue. It consists of a single 400 MW battery component and is slated to interconnect at the Gowanus Substation 345 kV.
Generated from interconnection queue and public data sources
State
NJ
County
Hudson
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
AMBAR POWER HOLDCO LLC
Utility
ConED
Entity
NYISO
Service Type
—
Point of Interconnection
Gowanus Substation 345 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- GOWANUS_GT2_1
- POI Substation
- Gowanus Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bayonne Energy Storage II