Town Line Solar CSR Phase I
240 MW hybrid in Sullivan, NY · In queue since October 2024 · Proposed COD December 2027
240 MW
Capacity
1
Components
Solar
1y 7m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The Town Line Solar CSR Phase I project is a proposed 240 MW solar and battery hybrid project located in Sullivan County, New York. Developed by RWE Solar Development, LLC, the project consists of 240 MW of solar generation. It is interconnected to the NYISO queue under queue ID NYISO-C24-363, with an entry date of October 15, 2024, and a proposed commercial operation date of December 1, 2027.
The project is slated to connect to the Coopers Corner to Middletown Tap 345 kV Line. The designated utility is NYPA, and the project is currently listed as active within the NYISO interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Sullivan
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
RWE Solar Development, LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Coopers Corner to Middletown Tap 345 kV Line
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE G
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SHOEMAKER___GT
- POI Substation
- Middletown Tap
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Town Line Solar CSR Phase I