Huntley Energy Storage
300 MW storage in Erie, NY · In queue since October 2024 · Proposed COD December 2029
300 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
Huntley Energy Storage is a proposed 300 MW battery storage project located in Erie County, New York. The project, developed by CEDAR HOLDCO LLC, is interconnected to the NYISO grid under queue ID NYISO-C24-368. The project entered the interconnection queue on October 15, 2024, and has a proposed commercial operation date of December 1, 2029. The point of interconnection is the Huntley 230 kV Substation.
The Huntley Energy Storage project has been featured in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Erie
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
CEDAR HOLDCO LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Huntley 230 kV Substation
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HUNTLEY___63
- POI Substation
- Huntley Substation