Suffolk County Storage II (NYISO-CR24-1001) — Project Summary

Queue ID
NYISO-CR24-1001
Capacity
70 MW
Technology
Battery
Status
active
Location
Suffolk, NY
Region
NYISO
Developer
Suffolk County Energy Storage II, LLC
IA Status

Suffolk County Storage II

NYISO-CR24-1001BetaActiveBatteryNYISOLBNL

70 MW storage in Suffolk, NY · In queue since September 2024 · Proposed COD April 2028

70 MW

Capacity

1

Components

Battery

1y 8m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

3y 7m

Pre-Study0%
Queue EntrySep 18, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-01

About

Suffolk County Storage II is a proposed 70 MW battery storage project located in Suffolk County, New York. The project, developed by Suffolk County Energy Storage II, LLC, is interconnected to the Long Island Power Authority (LIPA) grid at the Southold 69kV station. It is currently listed as active in the New York Independent System Operator (NYISO) interconnection queue under queue ID NYISO-CR24-1001, with an entry date of September 18, 2024, and a proposed commercial operation date of April 1, 2028.

The project consists of 70 MW of battery storage capacity. It is in the NYISO interconnection queue. Recent news coverage has discussed the project.

Generated from interconnection queue and public data sources

Project Details

State

NY

County

Suffolk

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Suffolk County Energy Storage II, LLC

Utility

LIPA

Entity

NYISO

Service Type

Point of Interconnection

Southold 69kV station.

Data Source

LBNL

Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE K
Hub Confidence
HIGH
Nearest Node (Estimated)
ONONDAGA_REF_OCCRA
POI Substation
Southwood Station

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.