Arthur Kill Unit 2 Uprate
369.9 MW generation in Richmond, NY · In queue since October 2024 · Proposed COD May 2025
369.9 MW
Capacity
1
Components
Gas
1y 7m
In Queue
—
IA Status
COD target: 2025
Total Duration
7 months
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-01
Arthur Kill Unit 2 Uprate is a proposed generation project located in Richmond County, New York. The project, developed by Arthur Kill Power LLC, is a 369.9 MW gas-fired generation facility. It is listed in the NYISO interconnection queue as entry NYISO-CR24-1004, with a queue entry date of October 4, 2024, and a proposed commercial operation date of May 1, 2025. The point of interconnection is Freshkills 138kV, and the project is currently listed as active in the queue.
The proposed project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Richmond
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Arthur Kill Power LLC
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Freshkills 138kV
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Arthur Kill Unit 2 Uprate