Harmony 2
74.5 MW generation in Osceola, FL · In queue since December 2020 · Proposed COD December 2024
74.5 MW
Capacity
1
Components
Solar
5y 5m
In Queue
System Impact Study
IA Status
COD target: 2024
Total Duration
4 years
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-30
The Harmony 2 project is a proposed 74.5 MW solar generation project located in Osceola County, Florida. The project is listed in the Orlando Utilities Commission (OUC) interconnection queue as OUC-202003, with a queue entry date of December 9, 2020. The proposed commercial operation date is December 30, 2024. The project's interconnection status is currently in the System Impact Study phase.
The Harmony 2 project is linked to the existing Harmony Florida Solar II operating plant (EIA plant ID 67208). Recent news coverage has highlighted the project, with 11 articles appearing in industry, grid, and deals categories.
Generated from interconnection queue and public data sources
State
FL
County
Osceola
Grid Region
Southeast
Market
—
Developer
—
Utility
Orlando Utilities Commission
Entity
OUC
Service Type
—
Point of Interconnection
St Cloud East - Holopaw 230 kV (Rocky Pond Station)
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Harmony 2