Bull Creek (Osceola Generating Station)
555 MW generation in Osceola, FL · In queue since September 2021 · Proposed COD June 2025
555 MW
Capacity
1
Components
Gas
4y 8m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2025-06-01
The Bull Creek (Osceola Generating Station) project is a proposed 555 MW gas-fired generation project located in Osceola County, Florida. The developer is Orlando Utilities Commission (OUC). This project is listed in the queue as OUC-202110, with a queue entry date of September 28, 2021, and a proposed commercial operation date of June 1, 2025. The interconnection agreement for this project has been executed.
The project is interconnected to the grid at the Rocky Pond point of interconnection. Recent news coverage has discussed the development of this project.
Generated from interconnection queue and public data sources
State
FL
County
Osceola
Grid Region
Southeast
Market
—
Developer
—
Utility
Orlando Utilities Commission
Entity
OUC
Service Type
—
Point of Interconnection
Rocky Pond
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bull Creek (Osceola Generating Station)