Malta Project
225 MW storage in Brevard, FL · In queue since March 2023 · Proposed COD December 2026
225 MW
Capacity
1
Components
Battery
3y 2m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-30
The Malta Project is a proposed 225 MW battery storage project located in Brevard County, Florida. The project is being developed by Orlando Utilities Commission (OUC) and has appeared in recent news coverage. It is interconnected to the OUC Indian River Plant.
The project is listed in the Orlando Utilities Commission interconnection queue as OUC-202311, with an entry date of March 6, 2023. The proposed commercial operation date is December 30, 2026. The project's interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
FL
County
Brevard
Grid Region
Southeast
Market
—
Developer
—
Utility
Orlando Utilities Commission
Entity
OUC
Service Type
—
Point of Interconnection
OUC Indian River Plant
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26