PacifiCorp-1186
0.9 MW generation in Bannock, ID · In queue since October 2019 · Proposed COD May 2020
0.9 MW
Capacity
1
Components
Hydro
6y 7m
In Queue
IA Executed
IA Status
COD target: 2020
Total Duration
7 months
Schedule
73 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2020-05-01
PacifiCorp-1186 is a proposed 0.9 MW hydroelectric generation project located in Bannock County, Idaho. The project, developed by Commercial Energy Management, Inc., entered the PacifiCorp interconnection queue on October 23, 2019, with a proposed commercial operation date of May 1, 2020. The point of interconnection is Circuit LAV11 out of the Lava substation.
The project's interconnection agreement has been executed.
Generated from interconnection queue and public data sources
State
ID
County
Bannock
Grid Region
Mountain West
Market
—
Developer
Commercial Energy Management, Inc.
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Circuit LAV11 out of Lava substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-1186