PacifiCorp-443
34.56 MW hybrid in Crook, OR · In queue since October 2012 · Proposed COD June 2015
34.56 MW
Capacity
1
Components
Solar
13y 7m
In Queue
IA Executed
IA Status
Signed Jun 2020
Queue → IA
7y 8m
Total Duration
7y 8m
Schedule
132 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2015-06-30
PacifiCorp-443 is a proposed 34.56 MW hybrid solar and battery project located in Crook County, Oregon. The project, developed by Ponderosa Solar, LLC, consists of 34.56 MW of solar capacity. It is interconnected to the PacifiCorp grid at the Ponderosa substation.
The project is listed in the PacifiCorp interconnection queue with an entry date of October 16, 2012, and a proposed commercial operation date of June 30, 2015. The interconnection agreement for the project has been executed as of June 5, 2020.
Generated from interconnection queue and public data sources
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
Ponderosa Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Ponderosa substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-443