PacifiCorp-636
99 MW generation in Iron, UT · In queue since December 2014 · Proposed COD December 2016
99 MW
Capacity
1
Components
Solar
11y 5m
In Queue
IA Executed
IA Status
Signed Sep 2016
Queue → IA
1y 9m
IA → COD
3 months
Total Duration
1y 9m
Schedule
114 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2016-12-31
PacifiCorp-636 is a proposed 99 MW solar generation project located in Iron County, Utah. The project, developed by Rush Lake Solar, LLC, is interconnected to PacifiCorp via the Parowan-West Cedar line. It entered the PacifiCorp interconnection queue on December 3, 2014, with a proposed commercial operation date of December 31, 2016.
The interconnection agreement for PacifiCorp-636 was executed on September 9, 2016.
Generated from interconnection queue and public data sources
State
UT
County
Iron
Grid Region
Mountain West
Market
—
Developer
Rush Lake Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Parowan-West Cedar line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-636