PacifiCorp-715
120 MW generation in Uinta, WY · In queue since October 2015 · Proposed COD July 2017
120 MW
Capacity
1
Components
Wind
10y 7m
In Queue
IA Executed
IA Status
COD target: 2017
Total Duration
1y 9m
Schedule
108 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2017-07-01
PacifiCorp-715 is a proposed wind generation project with a total capacity of 120 MW. The project is located in Uinta County, Wyoming, and is being developed by Uinta Wind Energy, LLC. It is interconnected to the PacifiCorp system at the Canyon Compression-Railroad transmission line point of interconnection.
The project entered the PacifiCorp interconnection queue on October 29, 2015, with a proposed commercial operation date of July 1, 2017. The interconnection agreement (IA) for the project has been executed. The project has been mentioned in recent news coverage related to regulatory matters.
Generated from interconnection queue and public data sources
State
WY
County
Uinta
Grid Region
Mountain West
Market
—
Developer
Uinta Wind Energy, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Canyon Compression-Railroad transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26