PacifiCorp-719
280 MW generation in Albany, WY · In queue since November 2015 · Proposed COD December 2018
280 MW
Capacity
1
Components
Wind
10y 6m
In Queue
Suspended
IA Status
Signed Sep 2022
Queue → IA
6y 10m
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–36 months
Proposed COD: 2018-12-31
PacifiCorp-719 is a proposed wind generation project with a total capacity of 280 MW. The project, located in Albany County, Wyoming, is being developed by Two Rivers Wind, LLC and is interconnected to PacifiCorp via the Freezeout substation. It entered the PacifiCorp interconnection queue on November 11, 2015, with a proposed commercial operation date of December 31, 2018.
The project's interconnection agreement (IA) status is currently listed as Suspended, with an IA date of September 2, 2022. The overall project status is also listed as suspended. The development has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
WY
County
Albany
Grid Region
Mountain West
Market
—
Developer
Two Rivers Wind, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Freezeout substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14