PacifiCorp-741
40 MW generation in Klamath, OR · In queue since May 2016 · Proposed COD September 2018
40 MW
Capacity
1
Components
Solar
10 years
In Queue
Suspended
IA Status
Signed Dec 2017
Queue → IA
1y 7m
IA → COD
9 months
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2018-09-01
PacifiCorp-741 is a proposed 40 MW solar generation project located in Klamath County, Oregon. The project, under development by Aurora Solar, LLC, is interconnected to PacifiCorp via the Klamath Falls-Lone Pine 230 kV transmission line.
The project entered the PacifiCorp interconnection queue on May 6, 2016, with a proposed commercial operation date of September 1, 2018. The interconnection agreement (IA) status is currently listed as Suspended, with an IA date of December 6, 2017. The overall project status is also listed as suspended.
Generated from interconnection queue and public data sources
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
Aurora Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Klamath Falls-Lone Pine 230 kV transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.