PacifiCorp-781
80 MW generation in Tooele, UT · In queue since August 2016 · Proposed COD December 2018
80 MW
Capacity
1
Components
Solar
9y 9m
In Queue
IA Executed
IA Status
Signed Oct 2018
Queue → IA
2y 2m
IA → COD
2 months
Total Duration
2y 2m
Schedule
89 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2018-12-31
PacifiCorp-781 is a proposed 80 MW solar generation project located in Tooele County, Utah. The project, developed by Elektron Solar, LLC, is interconnected with PacifiCorp via the Craner Flat substation. It entered the PacifiCorp interconnection queue on August 1, 2016, with a proposed commercial operation date of December 31, 2018.
The project's Interconnection Agreement (IA) was executed on October 2, 2018, and its current status is listed as "IA Executed." The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
UT
County
Tooele
Grid Region
Mountain West
Market
—
Developer
Elektron Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Craner Flat substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.