PacifiCorp-784
80 MW hybrid in Natrona, WY · In queue since August 2016 · Proposed COD December 2018
80 MW
Capacity
1
Components
Solar
9y 9m
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
2y 4m
Schedule
89 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2018-12-30
PacifiCorp-784 is a proposed 80 MW hybrid solar and battery project located in Natrona County, Wyoming. Developed by Dinosolar, LLC, the project consists of 80 MW of solar generation paired with battery storage. It is interconnected to the PacifiCorp system at the Casper substation.
The project is listed in the PacifiCorp interconnection queue as entry number 784, with an original queue entry date of August 4, 2016. The proposed commercial operation date was December 30, 2018, and the interconnection agreement has been executed.
Generated from interconnection queue and public data sources
State
WY
County
Natrona
Grid Region
Mountain West
Market
—
Developer
Dinosolar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Casper substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN