PacifiCorp-786
100 MW generation in Summit, UT · In queue since August 2016 · Proposed COD December 2018
100 MW
Capacity
1
Components
Wind
9y 9m
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
2y 4m
Schedule
89 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2018-12-31
PacifiCorp-786 is a proposed 100 MW wind generation project located in Summit County, Utah. The developer is Echo Divide Wind, LLC, and the project is interconnected with PacifiCorp via the Evanston-Anschutz transmission line.
The project is listed in the PacifiCorp interconnection queue with an entry date of August 4, 2016, and a proposed commercial operation date of December 31, 2018. The interconnection agreement (IA) for the project has been executed.
Generated from interconnection queue and public data sources
State
UT
County
Summit
Grid Region
Mountain West
Market
—
Developer
Echo Divide Wind, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Evanston-Anschutz transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-786