PacifiCorp-789
74.9 MW hybrid in Fremont, WY · In queue since August 2016 · Proposed COD September 2019
74.9 MW
Capacity
1
Components
Solar
9y 9m
In Queue
IA Executed
IA Status
COD target: 2019
Total Duration
3y 1m
Schedule
80 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2019-09-30
PacifiCorp-789 is a proposed 74.9 MW hybrid solar and battery project located in Fremont County, Wyoming. The developer is Fresh Air Energy II, LLC. The project consists of 74.9 MW of solar capacity.
The project is interconnected to the PacifiCorp system via the Riverton-Thermopolis transmission line. It entered the PacifiCorp interconnection queue on August 8, 2016, with a proposed commercial operation date of September 30, 2019. The interconnection agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
WY
County
Fremont
Grid Region
Mountain West
Market
—
Developer
Fresh Air Energy II, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Riverton-Thermopolis transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-789