PacifiCorp-801
80 MW hybrid in Natrona, WY · In queue since September 2016 · Proposed COD June 2019
80 MW
Capacity
1
Components
Solar
9y 8m
In Queue
IA Executed
IA Status
COD target: 2019
Total Duration
2y 9m
Schedule
83 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2019-06-30
PacifiCorp-801 is a proposed 80 MW hybrid solar and battery project located in Natrona County, Wyoming. The developer is Dinosolar, LLC. The project consists of 80 MW of solar generation, paired with battery storage.
The project is in the PacifiCorp interconnection queue, with an entry date of September 20, 2016. The proposed commercial operation date is June 30, 2019, and the Interconnection Agreement has been executed. The point of interconnection is the Bar Nunn substation.
Generated from interconnection queue and public data sources
State
WY
County
Natrona
Grid Region
Mountain West
Market
—
Developer
Dinosolar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Bar Nunn substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.