PacifiCorp-823
178 MW generation in Emery, UT · In queue since November 2016 · Proposed COD June 2019
178 MW
Capacity
1
Components
Solar
9y 6m
In Queue
IA Executed
IA Status
COD target: 2019
Total Duration
2y 7m
Schedule
83 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2019-06-30
PacifiCorp-823 is a proposed solar generation project with a total capacity of 178 MW, located in Emery County, Utah. The project is being developed by PacifiCorp Energy Supply Management and is interconnected with PacifiCorp. It is listed in the PacifiCorp interconnection queue as of November 15, 2016, with a proposed commercial operation date of June 30, 2019. The project's interconnection agreement has been executed.
The proposed project has been the subject of recent news coverage, with seven articles categorized as industry-related and concerning development.
Generated from interconnection queue and public data sources
State
UT
County
Emery
Grid Region
Mountain West
Market
—
Developer
PacifiCorp Energy Supply Management
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Emery substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14
View all articlesNo ask pi reports yet for this entity.
ask pi about Project PacifiCorp-823