PacifiCorp-846
75 MW generation in Tooele, UT · In queue since January 2017 · Proposed COD June 2019
75 MW
Capacity
1
Components
Solar
9y 4m
In Queue
IA Executed
IA Status
COD target: 2019
Total Duration
2y 5m
Schedule
83 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2019-06-30
PacifiCorp-846 is a proposed 75 MW solar generation project located in Tooele County, Utah. The project, under development by Horseshoe Solar, LLC, is interconnected to the PacifiCorp system at the Horseshoe substation.
The project is listed in the PacifiCorp interconnection queue with an entry date of January 10, 2017, and a proposed commercial operation date of June 30, 2019. The interconnection agreement for the project has been executed.
Generated from interconnection queue and public data sources
State
UT
County
Tooele
Grid Region
Mountain West
Market
—
Developer
Horseshoe Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Horseshoe substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.