PacifiCorp-905
50 MW hybrid in Klamath, OR · In queue since July 2017 · Proposed COD December 2019
50 MW
Capacity
1
Components
Solar
8y 10m
In Queue
IA Executed
IA Status
COD target: 2019
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–30 months
Proposed COD: 2019-12-01
PacifiCorp-905 is a proposed 50 MW hybrid solar and battery project located in Klamath County, Oregon. The development project, sponsored by Fresh Air Energy II, LLC, consists of 50 MW of solar generation capacity. The project is interconnected to PacifiCorp via the Copco 2 - Westside Tap to Klamath Falls line (Line 18).
The project entered the PacifiCorp interconnection queue on July 12, 2017, with a proposed commercial operation date of December 1, 2019. The interconnection agreement (IA) has been executed, and the project's current status is listed as suspended.
Generated from interconnection queue and public data sources
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
Fresh Air Energy II, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Copco 2 - Westside Tap to Klamath Falls line (Line 18)
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-905