PacifiCorp-958
21.17 MW generation in Lincoln, WY · In queue since October 2017 · Proposed COD February 2020
21.17 MW
Capacity
1
Components
Other
8y 7m
In Queue
Suspended
IA Status
COD target: 2020
Total Duration
2y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-02-01
PacifiCorp-958 is a proposed 21.17 MW generation project located in Lincoln County, Wyoming. The project, developed by Ormat Nevada, Inc., utilizes an unspecified "Other" technology. It is interconnected to the PacifiCorp system at the Lima substation.
The project entered the PacifiCorp interconnection queue on October 11, 2017, with a proposed commercial operation date of February 1, 2020. Its interconnection agreement status is currently listed as "Suspended."
Generated from interconnection queue and public data sources
State
WY
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
Ormat Nevada, Inc.
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Lima substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-958