PacifiCorp-974
80 MW generation in Lincoln, WY · In queue since November 2017 · Proposed COD December 2019
80 MW
Capacity
1
Components
Solar
8y 6m
In Queue
Suspended
IA Status
COD target: 2019
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2019-12-31
PacifiCorp-974 is a proposed 80 MW solar generation project located in Lincoln County, Wyoming. The project, under development by Lincoln Solar, LLC, is interconnected to the PacifiCorp system via the Naughton-Treasureton transmission line. It entered the PacifiCorp interconnection queue on November 15, 2017, with an original proposed commercial operation date of December 31, 2019.
The interconnection agreement status is currently listed as "Suspended," matching the overall project status in the queue.
Generated from interconnection queue and public data sources
State
WY
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
Lincoln Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Naughton-Treasureton transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.