PacifiCorp-C1-23
300 MW hybrid in Klamath, OR · In queue since May 2021 · Proposed COD December 2025
300 MW
Capacity
1
Components
Solar
5 years
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
4y 7m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-12-01
PacifiCorp-C1-23 is a proposed 300 MW hybrid solar and battery project located in Klamath County, Oregon. The project, developed by Sugar Pine Solar Project LLC, consists of 300 MW of solar capacity. It is listed in the PacifiCorp interconnection queue as of May 7, 2021, with a proposed commercial operation date of December 1, 2025. The project's interconnection agreement (IA) has been executed.
The point of interconnection (POI) for the project is the Chiloquin-LaPine transmission line. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
Sugar Pine Solar Project LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Chiloquin-LaPine transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C1-23