PacifiCorp-C1-37
199 MW hybrid in Kittitas, WA · In queue since May 2021 · Proposed COD December 2024
199 MW
Capacity
1
Components
Solar
5 years
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PacifiCorp-C1-37 is a proposed 199 MW hybrid solar and battery project located in Kittitas County, Washington. The development project, under the name Badger Gap PV I, LLC, consists of 199 MW of solar capacity. It is interconnected to the PacifiCorp system at the Pomona-Vantage transmission line.
The project entered the PacifiCorp interconnection queue on May 14, 2021, with a proposed commercial operation date of December 31, 2024. Its interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
WA
County
Kittitas
Grid Region
Mountain West
Market
—
Developer
Badger Gap PV I, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Pomona-Vantage transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C1-37