PacifiCorp-C1-39
300 MW hybrid in Washington, UT · In queue since May 2021 · Proposed COD June 2023
300 MW
Capacity
1
Components
Solar
5 years
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
2y 1m
Schedule
35 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2023-06-15
PacifiCorp-C1-39 is a proposed 300 MW solar and battery hybrid project located in Washington County, Utah. The project, developed by REBU BN, LLC, consists of 300 MW of solar capacity. It is interconnected to the PacifiCorp system at the Red Butte Three Peaks Sigurd transmission line.
The project is listed in the PacifiCorp interconnection queue with an entry date of May 14, 2021, and a proposed commercial operation date of June 15, 2023. The interconnection agreement (IA) for the project has been executed.
Generated from interconnection queue and public data sources
State
UT
County
Washington
Grid Region
Mountain West
Market
—
Developer
REBU BN, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Red Butte Three Peaks Sigurd transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C1-39