PacifiCorp-C1-40
150 MW hybrid in Yakima, WA · In queue since May 2021 · Proposed COD October 2025
150 MW
Capacity
1
Components
Solar
5 years
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-01
PacifiCorp-C1-40 is a proposed 150 MW hybrid solar and battery project located in Yakima County, Washington. The development project, under the name CG Yakima County Solar I LLC, consists of 150 MW of solar capacity. It is interconnected to the Midway-Union Gap transmission line.
The project entered the PacifiCorp interconnection queue on May 14, 2021, with a proposed commercial operation date of October 1, 2025. Its interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
WA
County
Yakima
Grid Region
Mountain West
Market
—
Developer
CG Yakima County Solar I LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Midway-Union Gap transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.