PacifiCorp-C1-44
400 MW hybrid in Lake, OR · In queue since May 2021 · Proposed COD October 2025
400 MW
Capacity
1
Components
Solar
5 years
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-01
PacifiCorp-C1-44 is a proposed 400 MW hybrid solar and battery project located in Lake County, Oregon. The development project, proposed by Archway Solar Energy LLC, consists of 400 MW of solar generation capacity. It is interconnected to the Burns-Summer Lake transmission line.
The project entered the PacifiCorp interconnection queue on May 14, 2021, with a proposed commercial operation date of October 1, 2025. Its interconnection agreement status is currently listed as suspended. The overall queue status is also suspended.
Generated from interconnection queue and public data sources
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
Archway Solar Energy LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Burns-Summer Lake transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C1-44