PacifiCorp-C1-46
198.75 MW hybrid in Klamath, OR · In queue since May 2021 · Proposed COD October 2024
198.75 MW
Capacity
1
Components
Solar
5 years
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-01
PacifiCorp-C1-46 is a proposed 198.75 MW hybrid solar and battery project located in Klamath County, Oregon. The development project, proposed by Diamond Solar Energy LLC, consists of 198.75 MW of solar capacity. Interconnection is requested with PacifiCorp via the Chiloquin-LaPine transmission line. The project entered the PacifiCorp interconnection queue on May 14, 2021, with a proposed commercial operation date of October 1, 2024. Its interconnection agreement status is currently listed as suspended.
The proposed project is currently listed as suspended in the interconnection queue. It has been the subject of recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
Diamond Solar Energy LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Chiloquin-LaPine transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26