PacifiCorp-C1-51
300 MW hybrid in Juab, UT · In queue since May 2021 · Proposed COD October 2024
300 MW
Capacity
1
Components
Solar
5 years
In Queue
Suspended
IA Status
COD target: 2024
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-01
PacifiCorp-C1-51 is a proposed 300 MW hybrid solar and battery project located in Juab County, Utah. The project, developed by Thirsty Valley Solar Energy LLC, consists of 300 MW of solar capacity. It is interconnected to the PacifiCorp system at the Clover substation.
The project entered the PacifiCorp interconnection queue on May 14, 2021, with a proposed commercial operation date of October 1, 2024. Its interconnection agreement status is currently listed as suspended. The overall queue status is also suspended.
Generated from interconnection queue and public data sources
State
UT
County
Juab
Grid Region
Mountain West
Market
—
Developer
Thirsty Valley Solar Energy LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Clover substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.