PacifiCorp-C1-54
199 MW hybrid in Utah, UT · In queue since May 2021 · Proposed COD October 2024
199 MW
Capacity
1
Components
Solar
5 years
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
3y 5m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2024-10-31
PacifiCorp-C1-54 is a proposed 199 MW hybrid solar and battery project located in Utah County, Utah. The project, developed by Pinyon Creek Solar LLC, consists of 199 MW of solar capacity. It is interconnected to the PacifiCorp system at the Mercer-Mona #1 transmission line.
The project is listed in the PacifiCorp interconnection queue with an entry date of May 14, 2021, and a proposed commercial operation date of October 31, 2024. The interconnection agreement for the project has been executed.
Generated from interconnection queue and public data sources
State
UT
County
Utah
Grid Region
Mountain West
Market
—
Developer
Pinyon Creek Solar LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Mercer-Mona #1 transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C1-54