Project PacifiCorp-C2-02 — Project Summary

Queue ID
PacifiCorp-C2-02
Capacity
199.9 MW
Technology
Battery
Status
active
Location
Juab, UT
Region
West
Developer
PacifiCorp
IA Status

PacifiCorp-C2-02

PacifiCorp-C2-02BetaActiveBatteryPacifiCorpLBNL

199.9 MW storage in Juab, UT · In queue since April 2022 · Proposed COD December 2026

199.9 MW

Capacity

1

Components

Battery

4y 1m

In Queue

IA Status

COD target: 2026

Interconnection

Total Duration

4y 8m

Pre-Study0%
Queue EntryApr 1, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-15

About

PacifiCorp-C2-02 is a proposed 199.9 MW battery storage project located in Juab County, Utah. The development project, under the ownership of PacifiCorp, entered the PacifiCorp interconnection queue on April 1, 2022. The proposed commercial operation date is December 15, 2026. The point of interconnection is the Clover substation.

The project consists of a single 199.9 MW battery component. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

UT

County

Juab

Grid Region

Mountain West

Market

Developer

PacifiCorp

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

Point of Interconnection

Clover substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PacifiCorp-C2-02