PacifiCorp-C2-05
199.9 MW storage in Juab, UT · In queue since April 2022 · Proposed COD December 2026
199.9 MW
Capacity
1
Components
Battery
4y 1m
In Queue
—
IA Status
COD target: 2026
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-15
PacifiCorp-C2-05 is a proposed 199.9 MW battery storage project located in Juab County, Utah. The development project, sponsored by PacifiCorp, consists entirely of battery storage. It is currently active in the PacifiCorp interconnection queue, with an entry date of April 1, 2022, and a proposed commercial operation date of December 15, 2026. The point of interconnection is the Mona substation.
The project is located in the western region of the United States. As of the latest data, the project does not have an interconnection agreement (IA) in place, nor is it linked to an existing operating plant in the EIA database. There is no indication of recent news coverage related to this project.
Generated from interconnection queue and public data sources
State
UT
County
Juab
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Mona substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-05