PacifiCorp-C2-07
80 MW hybrid in Crook, OR · In queue since April 2022 · Proposed COD May 2026
80 MW
Capacity
1
Components
Solar
4y 1m
In Queue
—
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-30
PacifiCorp-C2-07 is a proposed 80 MW hybrid solar and battery project located in Crook County, Oregon. The development project consists of 80 MW of solar capacity. It is listed in the PacifiCorp interconnection queue as of April 1, 2022, with a proposed commercial operation date of May 30, 2026. The point of interconnection is the Baldwin Road-Ponderosa transmission line.
The project is currently listed as active in the interconnection queue. No developer is specified in the queue data. No information is available regarding an interconnection agreement or news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Baldwin Road-Ponderosa transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-07