PacifiCorp-C2-106
400 MW generation in Lincoln, WY · In queue since May 2022 · Proposed COD December 2025
400 MW
Capacity
1
Components
Wind
4 years
In Queue
—
IA Status
COD target: 2025
Total Duration
3y 7m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PacifiCorp-C2-106 is a proposed 400 MW wind generation project located in Lincoln County, Wyoming. The project is listed in PacifiCorp's interconnection queue with an entry date of May 13, 2022. The proposed commercial operation date is December 31, 2025. The point of interconnection is the Naughton-Ben Lomond #2 transmission line.
The project is currently listed as active in the interconnection queue. No interconnection agreement status is available. There is no indication of an EIA plant match or recent news coverage.
Generated from interconnection queue and public data sources
State
WY
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Naughton-Ben Lomond #2 transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-106