PacifiCorp-C2-11
26 MW generation in Carbon, WY · In queue since April 2022 · Proposed COD March 2023
26 MW
Capacity
1
Components
Wind
4y 1m
In Queue
Facility Study
IA Status
COD target: 2023
Total Duration
11 months
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-03-01
PacifiCorp-C2-11 is a proposed wind generation project located in Carbon County, Wyoming, with a total capacity of 26 MW. The development project, sponsored by PacifiCorp, consists of 26 MW of wind generation capacity.
The project is currently active in the PacifiCorp interconnection queue as entry C2-11, with a queue entry date of April 6, 2022. The proposed commercial operation date is March 1, 2023, and the interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the Shirley Basin substation.
Generated from interconnection queue and public data sources
State
WY
County
Carbon
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Shirley Basin substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-11