PacifiCorp-C2-12
42 MW generation in Converse, WY · In queue since April 2022 · Proposed COD March 2023
42 MW
Capacity
1
Components
Wind
4y 1m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
11 months
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2023-03-01
PacifiCorp-C2-12 is a proposed 42 MW wind generation project located in Converse County, Wyoming. The development project, sponsored by PacifiCorp, entered the PacifiCorp interconnection queue on April 6, 2022, with a proposed commercial operation date of March 1, 2023. The project's interconnection agreement has been executed.
The proposed project will interconnect at the Windstar substation.
Generated from interconnection queue and public data sources
State
WY
County
Converse
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Windstar substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-12