PacifiCorp-C2-13
30 MW generation in Carbon, WY · In queue since April 2022 · Proposed COD March 2023
30 MW
Capacity
1
Components
Wind
4y 1m
In Queue
Facility Study
IA Status
COD target: 2023
Total Duration
11 months
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-03-01
PacifiCorp-C2-13 is a proposed 30 MW wind generation project located in Carbon County, Wyoming. The development project, sponsored by PacifiCorp, entered the PacifiCorp interconnection queue on April 6, 2022. Its proposed commercial operation date is March 1, 2023. The project's interconnection status is currently in the Facility Study phase, and its point of interconnection is the Foote Creek substation.
The project consists of 30 MW of wind generation capacity. It is located in the western region of the United States.
Generated from interconnection queue and public data sources
State
WY
County
Carbon
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Foote Creek substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-13