PacifiCorp-C2-131
199 MW hybrid in Emery, UT · In queue since May 2022 · Proposed COD December 2026
199 MW
Capacity
1
Components
Solar
4 years
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
PacifiCorp-C2-131 is a proposed 199 MW hybrid solar and battery project located in Emery County, Utah. The development project consists of 199 MW of solar generation capacity. It is listed as active in the PacifiCorp interconnection queue (queue entry date: May 14, 2022) with a proposed commercial operation date of December 1, 2026.
The interconnection request is currently in the Facility Study phase. The point of interconnection is the Camp Williams-Four Corners transmission line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
UT
County
Emery
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Camp Williams-Four Corners transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-131