50 MW hybrid in Iron, UT · In queue since May 2022 · Proposed COD December 2026
50 MW
Capacity
1
Components
Solar
4 years
In Queue
—
IA Status
COD target: 2026
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
PacifiCorp-C2-136 is a proposed 50 MW hybrid solar and battery project located in Iron County, Utah. The development project consists of 50 MW of solar generation. It is listed in the PacifiCorp interconnection queue as of May 14, 2022, with a proposed commercial operation date of December 1, 2026. The point of interconnection is the Pintura substation.
The project is currently listed as active in the interconnection queue. There is no information available regarding an executed interconnection agreement or news coverage.
Generated from interconnection queue and public data sources
State
UT
County
Iron
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Pintura substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.