Project PacifiCorp-C2-136 — Project Summary

Queue ID
PacifiCorp-C2-136
Capacity
50 MW
Technology
Solar+Battery
Status
active
Location
Iron, UT
Region
West
Developer
IA Status

PacifiCorp-C2-136

PacifiCorp-C2-136BetaActiveSolarBatteryPacifiCorpLBNL

50 MW hybrid in Iron, UT · In queue since May 2022 · Proposed COD December 2026

50 MW

Capacity

1

Components

Solar

4 years

In Queue

IA Status

COD target: 2026

Interconnection

Total Duration

4y 7m

Pre-Study0%
Queue EntryMay 14, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

About

PacifiCorp-C2-136 is a proposed 50 MW hybrid solar and battery project located in Iron County, Utah. The development project consists of 50 MW of solar generation. It is listed in the PacifiCorp interconnection queue as of May 14, 2022, with a proposed commercial operation date of December 1, 2026. The point of interconnection is the Pintura substation.

The project is currently listed as active in the interconnection queue. There is no information available regarding an executed interconnection agreement or news coverage.

Generated from interconnection queue and public data sources

Project Details

State

UT

County

Iron

Grid Region

Mountain West

Market

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

Point of Interconnection

Pintura substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PacifiCorp-C2-136