Queue ID
PacifiCorp-C2-14
Capacity
28 MW
Technology
Wind
Status
active
Location
Carbon, WY
Region
West
Developer
PacifiCorp
IA Status
IA Executed

PacifiCorp-C2-14

PacifiCorp-C2-14BetaActiveWindPacifiCorpLBNL

28 MW generation in Carbon, WY · In queue since April 2022 · Proposed COD March 2023

28 MW

Capacity

1

Components

Wind

4y 1m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection

Total Duration

11 months

Schedule

39 months past proposed COD

Construction75%
Queue EntryApr 6, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2023-03-01

About

PacifiCorp-C2-14 is a proposed wind generation project with a total capacity of 28 MW located in Carbon County, Wyoming. The developer and utility are both PacifiCorp. The project is interconnected to the Freezeout substation and is in the PacifiCorp interconnection queue, with an entry date of April 6, 2022. The proposed commercial operation date is March 1, 2023, and the Interconnection Agreement (IA) has been executed.

The development project consists of 28 MW of wind generation capacity. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

WY

County

Carbon

Grid Region

Mountain West

Market

Developer

PacifiCorp

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

Point of Interconnection

Freezeout substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PacifiCorp-C2-14