PacifiCorp-C2-15
6.6 MW generation in Carbon, WY · In queue since April 2022 · Proposed COD March 2023
6.6 MW
Capacity
1
Components
Wind
4y 1m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
11 months
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2023-03-01
PacifiCorp-C2-15 is a proposed wind generation project with a total capacity of 6.6 MW. The development is located in Carbon County, Wyoming, within the PacifiCorp service area. The project, sponsored by PacifiCorp, entered the PacifiCorp interconnection queue on April 6, 2022, and has an Interconnection Agreement (IA) executed. The proposed commercial operation date (COD) is March 1, 2023, and the point of interconnection (POI) is the Foote Creek substation.
The project consists of 6.6 MW of wind generation capacity. It is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
WY
County
Carbon
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Foote Creek substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.