Project PacifiCorp-C2-156 — Project Summary

Queue ID
PacifiCorp-C2-156
Capacity
175 MW
Technology
Solar+Battery
Status
active
Location
Linn, OR
Region
West
Developer
IA Status
Facility Study

PacifiCorp-C2-156

PacifiCorp-C2-156BetaActiveSolarBatteryPacifiCorpLBNL

175 MW hybrid in Linn, OR · In queue since May 2022 · Proposed COD December 2026

175 MW

Capacity

1

Components

Solar

4 years

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection

Total Duration

4y 7m

Facilities Study50%
Queue EntryMay 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

About

PacifiCorp-C2-156 is a proposed 175 MW hybrid solar and battery project located in Linn County, Oregon. The development project consists of 175 MW of solar capacity. It is listed in the PacifiCorp interconnection queue (queue entry date: May 15, 2022) with a proposed commercial operation date of December 1, 2026. The project's interconnection status is currently in the Facility Study phase, and the point of interconnection is the Alvey-Fry transmission line.

Generated from interconnection queue and public data sources

Project Details

State

OR

County

Linn

Grid Region

Mountain West

Market

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

Point of Interconnection

Alvey-Fry transmission line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.