PacifiCorp-C2-162
86 MW hybrid in Yakima, WA · In queue since May 2022 · Proposed COD November 2024
86 MW
Capacity
1
Components
Solar
4 years
In Queue
—
IA Status
COD target: 2024
Total Duration
2y 6m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-30
PacifiCorp-C2-162 is a proposed 86 MW hybrid solar and battery project located in Yakima County, Washington. The development project consists of 86 MW of solar generation. It is listed in the PacifiCorp interconnection queue as of May 15, 2022, with a proposed commercial operation date of November 30, 2024. The point of interconnection is the Tieton substation.
The project is listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
WA
County
Yakima
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Tieton substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-162