PacifiCorp-C2-167
125 MW generation in Emery, UT · In queue since May 2022 · Proposed COD May 2026
125 MW
Capacity
1
Components
Solar
4 years
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
4 years
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-01
PacifiCorp-C2-167 is a proposed 125 MW solar generation project located in Emery County, Utah. The project, being developed by PacifiCorp, entered the PacifiCorp interconnection queue on May 15, 2022, with a proposed commercial operation date of May 1, 2026. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is the Huntington-Pinto transmission line.
The development project has been the subject of recent news coverage, with two articles focusing on regulatory and development aspects.
Generated from interconnection queue and public data sources
State
UT
County
Emery
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Huntington-Pinto transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14