PacifiCorp-C2-170
199 MW storage in Lake, OR · In queue since May 2022 · Proposed COD December 2026
199 MW
Capacity
1
Components
Battery
4 years
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PacifiCorp-C2-170 is a proposed 199 MW battery storage project located in Lake County, Oregon. The project, developed by PacifiCorp, entered the PacifiCorp interconnection queue on May 15, 2022, with a proposed commercial operation date of December 31, 2026. Its interconnection status is currently in the Facility Study phase.
The project consists entirely of battery storage, with a total capacity of 199 MW. The point of interconnection is the Summer Lake substation. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Summer Lake substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-170